SUCCESS CASE

Ford Cuautitlán

Problem
presented

Load Center Non-Compliance: Power Factor and Current Unbalance.

Solution
Diram

STATCOM +/- 3 MVAr @ 13.8 kV

  • Custom design tailored to your needs
  • The fastest solution for power factor correction
  • Less floor space required per KVAR
  • Type: containerized.

Result
obtained

  • STATCOM met the dynamic power demand
  • Reactive due to the operation of the substation.
  • An FP value of 0.97 is achieved 95% of the time.
  • Compliance with Network Code 2.0 parameters
  • There was a significant reduction in the current imbalance.