Problemática
presented

Incumplimiento del centro de carga, factor de potencia.

Solution
Diram

2 STATCOMs de +3MVAR @ 6kV

  • Custom design tailored to your needs
  • The fastest solution for power factor correction
  • Less floor space required per KVAR
  • Tipo: Exterior.

Result
obtained

  • The STATCOM met the dynamic reactive power demand required for the operation of the load center.
  • An FP value of 0.97 is achieved 95% of the time.
  • Cumplimiento con parametros de
  • Código de Red 2.0